Track the Project Timeline - Teviot
Teviot

Milestones

  • Teviot Listening Campaign

    2017

     

    -

     

    Complete

    Residents identify key improvements and express interest in regeneration. Teviot Residents’ Steering Group (RSG) established. Teviot RSG select Independent Tenant & Leaseholder Advisor (ITLA).
  • Planning for Real

    2018

     

    -

     

    Complete

    Teviot Planning for Real event, residents participate in event to shape regeneration offer. Teviot RSG approve proposed regeneration offer.
  • Community Ballot

    Spring 2019

     

    -

     

    Complete

    Ballot of estate residents in spring 2019 approved regeneration with 86% in favour on an 81% turnout.
  • Resident centred regeneration - visits

    Spring 2019

     

    -

     

    Winter 2019

    Teviot RSG undertake study visions to regeneration schemes across London and attend a programme of regeneration training.
  • Selection of partners

    2020

     

    -

     

    Spring 2021

    In consultation with residents, Hill was selected as development partners, and BPTW as lead masterplan architects.
  • Pre-design

    Spring 2021

     

    -

     

    August 2021

    Early engagement with residents and Tower Hamlets Council, and surveys and technical work to inform design.
  • First public consultation: principles

    October 2021

     

    -

     

    December 2021

    Initial public consultation on masterplan principles.
  • Residents’ co-design workshops

    September 2021

     

    -

     

    Summer 2022

    Workshops with the RSG to co-produce the detailed design.
  • Second public consultation

    Summer/ Autumn 2022

     

    -

     

    In Progress

  • Submit planning application

    Winter 2022

     

    -

     

    Upcoming

  • Planning approval

    Spring 2023

     

    -

     

    Upcoming

    Planning application considered by London Borough of Tower Hamlets.
  • Start of phase 1

    Spring 2024

     

    -

     

    Upcoming

    Start on site with the initial phase of new homes (subject to planning permission).
  • Phase 2

    2027

     

    -

     

    End date

  • Phase 3

    2031

     

    -

     

    End date

  • Phase 4

    2035

     

    -

     

    End date